Carrying out Live Working on the Monceau A and B substations – replacement of the tensioned “substation” and installation of additional equipment
Services provided
Unhooking and securing of the tension
Setting up and installation of the compensation system requested by ELIA between the insulator and the portal support
Hanging up of the tension with the compensation system on the poral support
Removing the tension in the clamp
Adjustment of the tension in relation to the temperature and the closing of the disconnector switch.
For the Monceau A substation, these actions were carried out on 9 outgoing feeders in single strands and on 2 outgoing feeders in a twin bundle
For the Monceau B substation, these actions were carried out on 4 outgoing feeders in single strands and on 2 outgoing feeders in a twin bundle
This service also included the provision of the necessary vehicles, the supply of the equipment required and the consumables needed for the worksite