Tenders open for construction phase of Nigeria’s TCN Northern Corridor project
RTE international, leader of the consortium responsible for managing and supervising the TCN Northern Corridor project, announces the opening of tenders for the construction and refurbishment of electrical infrastructure to reinforce the grid in north-west Nigeria. Launched in 2022 on behalf of the Transmission Company of Nigeria (TCN), the country’s electricity transmission system operator, the project is co-financed by the Nigerian government, the French Development Agency (AFD) and the European Union, with total funding of €240 million.
A transformative project for Nigeria’s power grid and the wider West African region
Phase 1 of the TCN Northern Corridor project involves the construction of more than 600 km of 330 kV high-voltage overhead lines, along with the construction or upgrade of seven electrical substations. The project’s objectives are aligned with Nigeria’s Energy Transition Plan: expanding access to electricity, supporting the transmission of power from the solar plants planned in the north of the country, and interconnecting the Nigerian grid with that of Niger.
While this substantial reinforcement of the transmission infrastructure aims to improve the quality of Nigeria’s power grid, it will also, more broadly, support low-carbon economic development in West Africa and the emergence of a regional electricity market under the aegis of the West African Power Pool (WAPP).
A multidisciplinary consortium, strengthened by MAI Group’s environmental expertise
Since 2022, RTE international has led a consortium comprising Colenco Consulting Ltd, one of Africa’s leading engineering firms, and Cabira, an engineering consultancy based in Côte d’Ivoire, to support TCN’s Project Implementation Unit (PIU) in the overall supervision of the project on the owner’s side. During the first phase of the project, the consortium carried out the feasibility and design studies to define the scope of works and prepare the tender documents for the selection of contractors.
To meet the environmental and social criteria set by AFD, RTE international brought in the teams of its subsidiary MAI Group by way of a contract amendment in early 2026. MAI Group consolidated the impact assessment, completing the sections on biodiversity and environmental protection in order to satisfy AFD’s requirements. This contribution demonstrates how MAI Group’s environmental and social expertise complements RTE international’s engineering and project management capabilities. It also highlights the potential of bringing the two entities together to meet the standards of both international funders and local clients.
Commissioning scheduled for 2029
The tender phase, comprising two lots for substations and two for overhead lines, is now open. The selection process will include a three-month tender period, two months of bid evaluation and two months of contract negotiations. The construction phase will then last around 30 months, with the consortium of RTE International, Colenco Consulting Ltd and Cabira overseeing the works through to commissioning, scheduled for 2029.
“At RTE International, we see an infrastructure project as a way to drive local development and improve living conditions, beyond the design of the assets themselves. With the Northern Corridor project, several million people will gain access to electricity and a better quality of supply, and hundreds of jobs will be created during the construction and subsequent operation of the grid. The project also contributes to the region’s energy transition and to the emergence of a common electricity market. It perfectly reflects our mission: putting our expertise in electricity transmission to work for meaningful, sustainable development,” says Veronika Milewski, CEO of RTE International. » souligne Veronika Milewski, CEO de RTE international.