RTE international supported TEIAŞ to study the stability of its network with the arrival of the Akkuyu nuclear power plant comprised of four 1200 MW units.

Services delivered

  • Presentation of the methodology of stability studies that RTE carries out in the context of nuclear generation.
  • Presentation of RTE’s practices in terms of the design of the Insulation Fault Protection Scheme.
  • Analysis of the current methodology that TEIAŞ uses in terms of stability and protection.
  • Recommendations for managing the protection design regarding stability and insulation fault protection.